Replace copy machines in copy center.



Initiative TitleReplace copy machines in copy center.
Submitted in Previous Year(s)No
Critical Information, Notes, Justification, Rationale

The current lease on the copy machines in the copy center expires in December. 

Consequences of this initiative not being funded

We may lose out on cost savings by not bidding out and replacing existing machines. With the cost of technology decreasing we should have a substantial savings by new lease agreement. 

Department GoalsReplace copy machines.
Programs
LocationsMain Campus
Estimated Completion Date
Will this initiative span multiple budget years?Yes
ImportanceHigh
Funding SourceOperating Budget
Created11/29/2017 2:20 pm
Updated11/29/2017 2:20 pm

Institutional Goals

Goal How will the initiative support this institutional goal?
To save the college money. To provide prompt and efficient printing services along with printing options to complete various types of requested department projects.

Action Steps

Action Step Responsible Party Order
Replace copy machines in copy center. Facilities Project Manager 1

Expected Outcomes

Outcome Order
To provide a continuous prompt and efficient service on a daily basis along with cost savings. 1

Assessment Methods

Method Description Other Method Responsible Party
Tracking Usage of programs, services, participation can be tracked; demographic information may also be able to be collected. Facilities Project Manager

Resources

INITIAL YEAR COST: $50,000.00
RECURRING COST: $50,000.00

Equipment

Need Cost (Initial/Recurring) Supporting Departments
Copy Machines in copy center. $50000.00 / 50000.00 (1st year)
  • Facilities and Administrative Services
TOTAL: $50,000.00 / $50,000.00

Facility

Need Cost (Initial/Recurring) Supporting Departments
TOTAL: $0.00 / $0.00

Supply

Need Cost (Initial/Recurring) Supporting Departments
TOTAL: $0.00 / $0.00

Staffing

Need Cost (Initial/Recurring) Supporting Departments
TOTAL: $0.00 / $0.00

Training

Need Cost (Initial/Recurring) Supporting Departments
TOTAL: $0.00 / $0.00

Marketing

Need Cost (Initial/Recurring) Supporting Departments
TOTAL: $0.00 / $0.00

Other

Need Cost (Initial/Recurring) Supporting Departments
TOTAL: $0.00 / $0.00

Prioritization

This is initiative is ready for prioritization.

Assessment

DateDepartment NameStatusCost to DateFunding Source 
No results found.